Location: South Texas
Purpose/Opportunity:
Our client needed consistent crew support for routine maintenance and integrity on their pipeline system in South Texas. This challenge is common in the pipeline maintenance and integrity sector, where reliability and expertise are critical for operational efficiency and safety.
Methods:
To address the client’s needs, we provided designated crews including supervisors, operators, welders, and craftsmen equipped with trucks, tools, and equipment to support operations. Our solution emphasized consistent crew deployment, leveraging their knowledge of the client’s pipeline system requirements and procedures.
Results/Benefits:
Over 14+ years, our crews consistently supported the client’s pipeline operations with an exceptional safety record. This project included maintaining a 40 to 50-hour weekly scheduled maintenance routine with a 7–8-man crew dedicated to the Corpus Christi area pipeline system.